    Hello all....

    Construction on my basement reno is to start the week of December 4th, with HT wiring hoping to be done the week of the 18th - 22nd. I will post pictures as the work begins and add more as progress begins.

    Here is a list of the gear I will be using in version three as I sold all my other gear when I sold the old house.

    Receiver: Denon AVR-X4400H
    Projector: Sony VPL-HW45ES
    Screen: Elunevision 4K Tab Tension
    TV: Sony Bravia (some 4K model, haven't decided)
    Speakers: Monitor Audio Silver 300 L/R
    Silver C350 Centre
    CT265FX (2 pairs)
    IWS-10 - 10" in wall sub & amp

    This is a single level theatre with no back row. It just didn't work in this layout. Theatre is about 18'x15'. I will be building another custom rack knocked out somewhere in a wall, but that will be decided once final framing is done.

    Thanks to Jeff from Sound Investment Home Theatre (a good friend of mine) who's been helping with this version.

    Cheers!
    Andrew
     
  2. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    Construction has commenced. Subfloor and framing started this past Monday and so far great progress.

    Pic 1 - Looking into the theatre space. There will be double pocket doors into the theatre.
    Pic 2 - Where the main viewing space will be
    Pic 3 - From the back of the theatre looking to the right side
    Pic 4 - Looking to the left side - utilities room on the other side
    Pic 5 - From the front of the theatre looking to the far side of the basement

    All framing should be done by the end of next week and cabling should be done on the 18-19th of December.

    Cheers!
     

    Attached Files:

  3. Peter Apruzzese

    Peter Apruzzese Producer

    Joined:
    Dec 20, 1999
    Messages:
    3,633
    Likes Received:
    1,348
    Trophy Points:
    4,110
    Real Name:
    Peter Apruzzese
    Nice! Looking forward to watching the progress.
     
  4. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    Thanks Peter,
    Wiring should hopefully commence the end of this week or Monday of next... that pesky 'work' thing gets in the way!
     
  5. Bobofbone

    Bobofbone Second Unit

    Joined:
    Jan 24, 2010
    Messages:
    253
    Likes Received:
    40
    Trophy Points:
    110
    Real Name:
    Bob
    t... that pesky 'work' thing gets in the way![/QUOTE]

    It does. But, look on the brighter side of it. Without the paycheck that comes with it, our theaters wouldn't be nearly as nice.

    Looking forward to seeing your progress!!
     
    Andrew Stoakley likes this.
  6. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    Well... after some trouble with a bad piece of MDF, the gear rack is fishinshed and ready for final painting.
    Wiring begins on Monday!
     

    Attached Files:

  7. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    Wiring is all finished! 7.1 system with in-ceiling surrounds and in-wall subwoofer. Went with the in-walls/ceilings to get high bride approval, which as we all know is very important. Lots of Cat6 and coax plus additional speaker wire for in ceiling stereo speakers setup with Sonos Connect amps to deliver basement wide music. Hemmed and hawed about adding conduit, but in the end, the way the theatre ceiling is designed, I could fish cable as opposed to having to put it in a tube.

    Electrical is up next followed by HVAC and plumbing!

    Project should hopefully be done by the end of January.

    Cheers!
    bar area Sonos speaker.JPG bulkhead surround speaker.JPG cables 1.JPG cables 2.JPG front wall wiring 2.JPG front wall wiring.JPG games room Sonos speaker.JPG in wall sub box.JPG projector mount area.JPG bar area Sonos speaker.JPG projector mount area.JPG in wall sub box.JPG games room Sonos speaker.JPG
     
  8. xx Brian xx

    xx Brian xx Stunt Coordinator

    Joined:
    Dec 18, 2017
    Messages:
    55
    Likes Received:
    11
    Trophy Points:
    10
    Real Name:
    Brian
    Room is looking great!
    The Sony projector should look really good at 120,000:1 contrast. I'm jealous.
    For the TV, I currently have the Sony 65X930D but will probably upgrade to the A1 because the slim back light doesn't thrill me. If the A1 is more than you want to spend, I would check out the 900E with full backlight array.

    Looking forward to more pictures as the project progresses.

    Brian
     
  9. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    Thanks!

    Yeah, my buddy who is helping me design the project loves the projector, he's got one in his house too! The TV will literally be a last minute decision as I'm at least two months away from the final install of all the gear. I have a really busy January and February for work (Olympic years are the worst in my field) and won't order the TV until I have some time :)

    All the electrical work should be done this week or at least mapped out with my electrician before the Christmas break. Fingers crossed.

    Cheers!
    Andrew
     
  10. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    UPDATE:

    Hey all, now that the Christmas break is over, got a lot more done in the theatre space. All the bulkheads are done, electrical is done and passed and insulation went in today. As you can see from the pics, the space is becoming more defined and the AV rack has to go into place with the remaining safe and sound before drywall. Really happy with how it's looking - can't wait for it to be done. Still on track for basement completion by the first week of February - but it could be till the end of March before any gear goes in the space due to work commitments (damn Olympics!)

    Cheers!
    Andrew AV rack space.JPG Entrance to theatre.JPG from back of theatre.JPG Front of theatre bulkhead.JPG Projector Housing.JPG projector mount area.JPG Projector mount.JPG
     
  11. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    6940F379-5BFD-49E9-8FEC-E1DA847A986F.jpeg B2C84943-468A-486B-ABF0-3699A56C1860.jpeg 9E0AF2C3-B52D-40E0-A6BB-3BF6193D9434.jpeg Drywall and AV rack enclosures are done! Really happy with how the space has come together. You can draw, plan and imagine all you want, but until you see it, you can never be 100%.

    It’s going to be a great space for movies, games friends and family.
     
    SAhmed likes this.
  12. Brian Dobbs

    Brian Dobbs Ambassador

    Joined:
    Jul 1, 2001
    Messages:
    1,046
    Likes Received:
    171
    Trophy Points:
    1,610
    Location:
    Maryland
    Real Name:
    Brian Dobbs
    So exciting to get drywall up, eh?
     
  13. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley

    Yes! Drywall was all finished today for the entire basement and not just the theatre room. Tapers and mudders are next week and then I should be painting the following hopefully.
     
  14. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    Drywall is all finished... last bits of trim to be done and then it's prime and paint time! About two weeks and it should all be done... minus the whole 'theatre' part as work is too busy to get it all put in. I'm hoping all the components will be in and setup by the end of March. Fingers crossed!!
     

    Attached Files:

  15. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    883602AD-F31B-421B-B9BC-6C9119C5B5D8.jpeg A6A43408-C6AA-49C7-A7B6-4455AF108DC5.jpeg 4F56756C-AEA3-44EC-BF83-5D1B39D04580.jpeg Update:

    Painting is all done! Electrical is almost done. Flooring will be going down on Monday. Still no timetable on actual gear install ¯\_(ツ)_/¯ (stoopid work)

    Really happy with the blue and white. It’ll match with the carpet really nicely.
     
    Sam Posten likes this.
  16. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    Well, flooring is in and I’m really happy how it all turned out. Next update won’t be till the actual gear goes in which will be around the 20th of March. Three long work road trips tend to hamper any play time.
    Thanks for all the comments. Can’t wait for it to finally get done!!
    6E589E4F-032B-4144-8345-6BB3938287E7.jpeg
    ADFBCD1A-7A52-4EEC-8B43-2A98296AD243.jpeg
     
  17. Andrew Stoakley

    Andrew Stoakley Stunt Coordinator

    Joined:
    Feb 27, 2004
    Messages:
    163
    Likes Received:
    4
    Trophy Points:
    110
    Real Name:
    Andrew Stoakley
    Hey everyone.
    Well, it's finished! Took over 12 hours to install yesterday, but she's in and it's time to start playing and tweaking.
    Lots to do still, but I'm loving it!
    Thanks for the all the comments and suggestions, it's much appreciated.
    Cheers!
    Andrew
     

    Attached Files:

    Bryan^H likes this.
  18. Bobofbone

    Bobofbone Second Unit

    Joined:
    Jan 24, 2010
    Messages:
    253
    Likes Received:
    40
    Trophy Points:
    110
    Real Name:
    Bob
    Very nice !!
     
    Andrew Stoakley likes this.